OAR GLERL LMFS Building 3 Replacement

Overview

ID #

13245889

Document Type

Environmental Assessment

NOAA Office

Office of the Chief Administrative Officer

Document Status

Complete

Last Updated

09/06/2017

Summary

To meet space demands, GLERL intends to demolish and rebuild Building #3 for use as additional laboratory, administrative, maintenance, and storage space. The current building is a one-story 2,500 square feet (sf) pre-engineered steel building constructed in approximately 1969 and used for storage and laboratory space. The proposed new structure will occupy the same building footprint but double the size to roughly 5,000 sf by addition of a second story. The proposed action includes the demolition of the existing building, with the possible exception of the exterior foundation walls.

Construction project is expected to be initiated in FY18